Timeline for Update of the Science Framework for California Public Schools
Suspended
Effective 7/28/2009
Approved by the State Board of Education July 9, 2008
Event |
Schedule |
|---|---|
Curriculum Commission action on update plan, timeline, and Curriculum Framework and Criteria Committee (CFCC) application |
May 15-16, 2008 |
State Board of Education (SBE) action on update plan, timeline, and CFCC application |
July 9-10, 2008 |
Recruitment of CFCC members (at least 90 days per CCR 5 Section 9513) |
August 2008 – November, 2008 |
Focus Groups meet to solicit public input on the framework update that will be forwarded to the Curriculum Commission and SBE. Meetings will be held at various County Offices of Education throughout the State. Specific dates to be determined:
|
October 2008 |
Curriculum Commission action on CFCC applications (recommendations to be forwarded to SBE for appointment). Commission also reviews scholarly input, Focus Group input on the framework and statutory requirements and recommendations. |
January 28-30, 2009 |
SBE action on CFCC recommendations and Focus Group input |
March 11-12, 2009 |
CFCC meets approximately every four weeks, for a total of five meetings to draft framework. Contracted framework writer to attend CFCC meetings and develop first drafts.
|
June-October, 2009 |
Curriculum Commission action to approve draft Framework for field review |
January 20-22, 2010 |
Required 60-day field review of draft Framework (required by CCR 5 Section 9515) |
January – March, 2010 |
Curriculum Commission meets to analyze field review results and revise draft framework |
April 12, 2010 (extra meeting) |
Curriculum Commission action on draft framework, includes public hearing and recommendation to SBE |
May 20-21, 2010 |
Required 60-day public review and comment on Curriculum Commission’s recommended framework (CCR 5 Section 9515) |
June – August 2010 |
SBE action on draft framework. SBE receives Curriculum Commission recommendations and holds public hearing before taking action. |
September 8-9, 2010 |
Document Preparation |
Winter 2010 |
Soonest that adoption can take place (30 month rule reduced to about 24 months) |
November 2012 |