CALPADS Project Milestones
A chronology of major activities, both completed and projected, related to the CALPADS project is displayed in the table below. For more details on system development and implementation go to Current Status.
Project Development
| Project Stage | Start | Completed | Approved/Released |
|---|---|---|---|
| Feasibility Study Report (FSR) | April 2004 | August 2004 | |
| FSR Submission 2 | January 2005 | April 2005 | June 2005 – Conditional |
| Supplemental Report to FSR | June 2005 | October 2005 | November 2005 |
| Request for Proposal (RFP) | December 2005 | June 2006 | September 2006 |
| Final Bids Submission/Evaluation | April 2007 | May 2007 | June 2007 |
| Final Bid Cost Opening | June 2007 | ||
| Special Project Report | July 2007 | September 2007 | November 2007 |
| Section 11 | November 2007 | December 2007 | December 2007 |
| Contract Commences | January 2008 |
System Development*
| Project Stage | Start | Proposed Completion | Completed |
|---|---|---|---|
| Phase 1: Project Initiation | January 2008 | May 2008 | |
| Phase 2: Design, Development, Conversion, Testing | April 2008 | April 2009 | |
| Phase 3: Pilot User Acceptance Test (UAT) | December 2008 | July 2009 | |
| Phase 4: System Implementation | April 2009 | June 2010 | |
| Phase 5: Warranty and Maintenance | July 2010 | June 2011 |
*Projected dates