CA Uniform Public Construction Cost Accounting Act
Provides an overview of CUPCCAA program and process that school districts can use to streamline procurement procedures and higher bid thresholds. Districts must formally elect participation and follow applicable laws, requirements and board policies.What is the California Uniform Public Construction Cost Accounting Act (CUPCCAA)?
CUPCCAA is a voluntary program that allows public agencies, including school districts, to use streamlined procedures and higher bidding thresholds for public works projects.
A district must formally elect to participate through adoption of a governing board resolution. Once adopted, the entire district becomes subject to CUPCCAA requirements. This is general information only, be sure to comply with all applicable statutes, county requirements, and district board rules, and consult with legal counsel as needed.
Electing to Participate
Why Districts Adopt CUPCCAA
Without CUPCCAA
- Construction projects exceeding $15,000 generally require formal bidding.
With CUPCCAA
- Projects of $75,000 or less may be completed without bidding.
- Projects between $75,001 and $220,000 may use informal bidding procedures.
- Projects exceeding $220,000 require formal bidding.
This provides districts with significantly greater flexibility for routine facility projects and maintenance work.
How to Implement CUPCCAA
Please see the California Uniform Construction Cost Accounting Commission Manual (CUCCAC) provided by the California State Controller’s Office at Cost Accounting Policies and Procedures Manual - 2025 Edition
(PDF)
Step 1: Adopt CUPCCAA
The governing board adopts a resolution that:
- Elects participation in CUPCCAA
- Adopts the State Controller's accounting procedures
- Establishes an implementation date
- Commits the district to complying with CUPCCAA requirements
Resource: Sample Board Resolution - See page 6 of the CUCCAC Manual
Step 2: Notify the State Controller
After board approval:
- Submit letter to State Controller’s Office to notify agency is opting into Act.
- Submit a copy of the adopted resolution to the State Controller's Office.
- Maintain documentation of the submission.
Step 3: Adopt Informal Bidding Procedures
The district should adopt procedures addressing:
- Informal bidding
- Contractor notifications – See pages 8-17 of the CUCCAC Manual
- Award procedures - See page 36 of the CUCCAC Manual
- Force account work
- Purchase orders
- Negotiated contracts
Resources:
Sample CUPCCAA Procedures Board Resolution (DOCX).
Sample letter to State Controller opting into Act (DOCX).
Step 4: Create and Maintain a Contractor List
See page 8 of the CUCCAC Manual for more information.
Solicit Contractors
- Publish a notice inviting contractors to register.
- Advertise during the annual registration period.
Maintain Contractor Information
- Business name
- Address
- Contact information
- Contractor license number
- License classification
- Type(s) of work performed
Ongoing Compliance Requirements
Districts participating in CUPCCAA must:
- Maintain contractor lists
- Follow applicable bid thresholds
- Avoid bid splitting
- Use proper notification procedures
- Follow adopted informal bidding policies
Failure to comply may jeopardize participation in the program.
More Information: California State Controller's Office – California Uniform Construction Cost Accounting Commission at California Uniform Construction Cost Accounting Commission
. This Commission webpage also includes a Participating Agencies List where you can verify whether your district is registered to participate.
Projects $75,000 or Less
Projects with an estimated cost of $75,000 or less do not require formal or informal bidding. Be sure to comply with all applicable statutes, county requirements, and district board rules, and consult with legal counsel as needed.
Available Procurement Methods
The district may complete the work using:
- Force Account
- District employees perform the work.
- Negotiated Contract
- The district contracts directly with a qualified contractor or vendor.
- Purchase Order
- The district issues a purchase order to complete the work.
Project Planning
Before selecting a procurement method, districts should:
1) Define the Scope
Determine:
- Work to be performed
- Materials required
- Labor needs
- Schedule requirements
- Special project conditions
2) Develop a Cost Estimate
A reasonable estimate helps ensure:
- Appropriate procurement method
- Budget compliance
- Accurate project planning
Benefits
Projects under this threshold can often be completed more quickly, with less administrative effort and lower procurement costs.
Informal Bidding Procedures
Projects estimated between $75,001 and $220,000 may utilize CUPCCAA's informal bidding process.
This process eliminates the need for traditional public advertisement while still maintaining competition.
Informal Bidding Process
The district typically:
- Prepares project documents.
- Identifies contractors from the CUPCCAA contractor list.
- Sends invitations to bid.
- Notify Trade Journals & Builders Exchanges outlined in CUCCAC Manual.
- Receives bids.
- Evaluates responsiveness and responsibility.
- Awards the contract.
Contractor Notifications
The district notifies:
- Contractors on the CUPCCAA list that perform the applicable trade work.
Notification may be provided through:
- Other approved notification methods
Districts must also notify:
- Notify Trade Journals & Builders Exchanges outlined in CUCCAC Manual sections 1.05 and 1.07.
Awarding the Contract
Contracts are generally awarded to the lowest responsive and responsible bidder.
Responsive Bidder
A responsive bidder:
- Submitted all required forms
- Followed bid instructions
- Met bid requirements
Responsible Bidder
A responsible bidder:
- Holds the appropriate license
- Has the capability to perform the work
- Demonstrates satisfactory qualifications and experience
- Has adequate financial and operational capacity
A contractor must be both responsive and responsible to receive award. Be sure to comply with all applicable statutes, county requirements, and district board rules, and consult with legal counsel as needed.
Exception
If all informal bids exceed $220,000 but are $235,000 or less:
- The governing board may award the contract by a four-fifths vote.
- The board must determine the original estimate was reasonable.
Key Difference from Formal Bidding
- No newspaper advertisement required.
- Shorter notice period.
- No public bid opening requirement.
Formal Public Bidding Required
Projects estimated to cost more than $220,000 must follow traditional public works bidding requirements.
Formal Bidding Process
The district:
- Develops plans and specifications.
- Prepares a Notice Calling for Bids.
- Provides required public notice.
- Receives sealed bids.
- Determines the lowest responsive and responsible bidder.
- Obtains governing board approval.
- Awards the contract.
Public Notice Requirements
Notice is generally provided through:
- Newspaper Advertisement
- Publication in a newspaper of general circulation.
- Publication in a newspaper of general circulation.
- Trade Publications and Contractor Resources
- Distribution to:
- Construction trade journals
- Plan rooms
- Contractor organizations
- Appropriate contractor lists
- Distribution to:
- Notice should be provided sufficiently in advance of bid opening.
Awarding the Contract
The district generally awards the contract to the lowest responsive and responsible bidder.
The successful bidder must:
- Meet all bid requirements
- Hold the required contractor license
- Demonstrate capability and capacity to perform the work
- Comply with all applicable public works requirements
Important Reminder
Projects may not be divided into smaller contracts to avoid bidding requirements. This practice, known as bid splitting, is prohibited under California public contracting laws.
Be sure to comply with all applicable statutes, county requirements, and district board rules, and consult with legal counsel as needed.
Using CUPCCAA for Maintenance
Why It Matters
Maintenance has different bidding requirements than public works. School districts may elect to use CUPCCAA thresholds for maintenance if maintenance is clearly included in the district's CUPCCAA resolution. *Note: If opting into maintenance, agency is now subject to a lower limit of $75,000.
Standard Maintenance Threshold
Formal bidding required when maintenance exceeds approximately $119,100.
The bid threshold is adjusted periodically by the State Superintendent of Public Instruction.
The current threshold became effective January 1, 2026 and can be found at California Department of Education Bid Threshold Letter.
These bid threshold letters are posted to the CDE website at Correspondence.
If Maintenance Is Included in CUPCCAA Resolution
The district may use the CUPCCAA three-tier process:
| Maintenance Cost | Procurement Method |
|---|---|
| Under $75,000 | Quotes/Proposals |
| $75,001-$220,000 | Informal Bid |
| Over $220,000 | Formal Bid |
Common Maintenance Examples
May qualify as maintenance:
- Minor repairs
- Routine replacement
- Preventive maintenance work
- Ongoing upkeep activities
Typically public works:
- Renovations
- Reconstruction
- Major replacement projects
- Alterations or improvements
- Painting/repainting projects that meet the public works definition
Important
Do not "flip-flop" between maintenance and public works classifications. Be consistent and follow your adopted CUPCCAA resolution.
Emergency Procurement Under CUPCCAA
An emergency is a sudden, unexpected occurrence that creates imminent danger to life, health, property, or essential public services requiring immediate action. See Chapter 2.5 starting on page 31 in the CUCCAC Manual.
Examples:
- Gas leak
- Storm-damaged facilities preventing school operations
- Dangerous structural failures
CUPCCAA Emergency Authority
For emergency work:
- Board may proceed immediately with repairs.
- No formal bidding required.
- 4/5 board vote required.
- Authority may be delegated to administration with required reporting back to the board.
CUPCCAA Best Practices
Follow the Three-Step Process Every Time
- Define project
- Estimate cost
- Select procurement method
Never start with procurement.
Avoid Bid Splitting
Do not divide one project into multiple smaller contracts simply to avoid a higher bidding threshold.
Use Written Construction Contracts
Even under $75,000:
- Use a formal contract.
- Include prevailing wage requirements.
- Include insurance requirements.
- Obtain payment bonds when required.
Maintain Good Documentation
Maintain:
- Project estimates
- Procurement records
- Bid notices
- Contract documents
- Board approvals
- Project accounting records
Notify Contractors Consistently
- Use your CUPCCAA contractor list.
- Notify trade journals when required.
- Consider website postings and email distribution for all opportunities.
Plan Ahead
Develop:
- Annual maintenance contracts
- Emergency response contracts
- Standard specifications
- Template bid documents
- Emergency procurement procedures