CAPSDAC 2.0 Phased Roll Out Timeline
California Preschool Data Collection (CAPSDAC) System, being referenced as CAPSDAC 2.0 for clarity until the first iteration is decommissioned.CAPSDAC 2.0 Phased Roll Out Timeline
CAPSDAC 1.0 is being retired August 1, 2026, after the certification of the June 2026 data.
CAPSDAC 2.0 is launching July 1, 2026, for the 2026–27 school year. There is a one-month overlap where both systems will be live. July 2026 data will be the first month’s data certified in the CAPSDAC 2.0 system.
CAPSDAC 2.0 launch is a phased roll out of data domains and certification.
Phases and Data Domains
- Phase 1, July 2026: Classroom, Staff, Staff Assignment, Staff Classroom, Child, Family, Language, Supplemental Language, Enrollment, and Classroom Enrollment.
- Phase 2, January 2027: Attendance and Education Program.
- Phase 3, 2030: Incident and Incident Result.
Phases and First Certification of Each Certification Type
Local Educational Agencies (LEAs) should submit data to CAPSDAC on an ongoing basis. However, during the monthly (monthly submission), the fall (fall submission), and at the end of the fiscal and traditional school year (end-of-year [EOY] submission), LEAs are required to review certification reports which reflect certain data which have been submitted to CAPSDAC.
- Monthly Certification: Enrollment Information (Phase 1), Attendance Information (Phase 2)
- First certification of Enrollment Information will be due in August 2026 of the July 2026 data.
- First certification of the Attendance information will be due in February 2027 of the January 2027 data.
- Fall: Information from all other records that is not certified in the monthly certification.
- First certification will be due in December 2027 and will be certifying a snapshot of the data as of Census Day (the first Wednesday of October).
- End of Year: Information from all other records that are not certified in the monthly certification.
- First certification will be due July 2027 of the data from the 2026–27 school/fiscal year.
Certification Timeline Table Example
The following certification timeline table is subject to change but is shared to provide a visual of the timeline for submitting and certifying data. Information is not yet finalized and can be superseded by updated versions.
| CAPSDAC Submission | Primary Data Submitted | Official Submission Window | Recommended Date for Zero Errors | Certification Deadline | Amendment Window |
|---|---|---|---|---|---|
| Monthly (Prior month's data) | Enrollment Information Attendance Information (Phase 2) |
First day of the month through the last day of the month | Not Applicable | 15th of the month | Certification deadline date through the last day of the month |
| Fall (Census Day data) | All Data Records Information Except Attendance and Enrollment | First Wednesday of October (Census Day) through late January
Example: October 6, 2027 to January 22, 2028 |
Two weeks prior to Certification Deadline
Example: November 19, 2027 |
Early/Mid December
Example: December 10, 2027 |
Certification Deadline through Late January
Example: December 10, 2027 through January 21, 2028 |
| End of Year (Cumulative data) | All Data Records Information Except Attendance and Enrollment | Beginning of May through end of July
Example: May 3, 2027 to July 30, 2027 |
Beginning of May through end of July
Example: May 3, 2027 to July 30, 2027 |
Mid July
Example: July 16, 2027 |
Certification Deadline through End of July
Example: July 19, 2027 through July 30, 2027 |